for consumers, producers and prosumers.
If you are a customer, producer or prosumer and you plan to connect a facility or generation source to our power grid or entrust us with the function of a distribution system operator on your infrastructure, use our services.
Below you will find the necessary information and documents to fill out and send to us.
Download
We will confirm the completeness of your application within 14 days and consider it within 21 days if you apply for a connection capacity of up to 40 kW and within 30 days if you apply for a higher capacity.
Do pobrania
We will confirm the completeness of your application within 14 days and consider it within 21 days if you apply for a connection capacity of up to 40 kW and within 30 days if you apply for a higher capacity.
We will confirm the completeness of your application within 14 days and consider it within 21 days if you apply for a connection capacity of up to 40 kW and within 30 days if you apply for a higher capacity.
Due to Commission Regulation (EU) 2016/631 of April 14, 2016 establishing the network code for the connection of generating units, we submit the procedure and document templates developed under PTPiREE, related to the requirements for testing connected energy generation modules.
In response, we will send you a proposal for a connection agreement with a set of attachments, which include the connection conditions. If there are any deficiencies in the application, we will inform you about it. You have 30 days to complete the application. After this time, the application is left without consideration.
You can use a qualified or traditional signature.
Please send the contract in electronic version to the following e-mail address: kontakt@enercogrid.pl
Address for sending paper contracts:
EnercoGrid Sp. z o. o.
ul. Gotarda 9
02-683 Warsaw
After meeting the requirements set out in the connection agreement, we will start the performance of the works specified in the connection conditions within the time limit resulting from the agreement.
After completing the work, we will notify you of our readiness to provide electricity distribution services. Then send us a completed application form for installation readiness for connection with attachments.
After we receive the above-mentioned installation readiness notification and process the connection fee, you will be able to conclude a comprehensive electricity distribution and sales agreement or a sales and electricity distribution agreement. Within 3 days from the conclusion of this contract, our electrician will inspect the prepared electrical installation, install the meter and supply voltage to the prepared installation.